Show new navigation
On
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74017 REL 58: 2002-060-00 EXP NEZ PERCE HARVEST MONITORING
Project Number:
Title:
Nez Perce Harvest Monitoring on Snake and Clearwater Rivers
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 50.00%
Upper Snake Snake Upper 50.00%
Contract Number:
74017 REL 58
Contract Title:
2002-060-00 EXP NEZ PERCE HARVEST MONITORING
Contract Continuation:
Previous: Next:
74017 REL 33: 2002-060-00 EXP NEZ PERCE HARVEST MONITORING
  • 74017 REL 78: 2002-060-00 EXP NEZ PERCE HARVEST MONITORING
Contract Status:
Closed
Contract Description:
This project describes the Nez Perce Tribe's efforts to monitor currently ongoing NPT fisheries.  Sampling strategies are designed to provide greater data precision in treaty catch reports and exploitation rates during select Nez Perce fishery seasons.  Harvest management is intertwined with all Columbia Basin artificial production programs (particularly BPA-funding hatchery facilities) and affects the status of naturally produced stocks as well.  The Nez Perce Tribe has monitored its fisheries primarily by funding sources outside the Northwest Power Planning Council (NPPC) process.  However, the subbasin planning process has documented the need to incorporate this very important aspect of fisheries management within the existing Fish and Wildlife Program.  

The work of the SOW is focused on actual on-the-ground harvest monitoring in Snake, Salmon and Clearwater rivers and their tributaries and ... in the Zone 6 fishery (Bonneville Dam to McNary Dam).  In addition, there will be work to design and verify the monitoring techniques and disseminate the monitoring data to cooperating agencies on a regular basis.   
Account Type(s):
Expense
Contract Start Date:
01/01/2020
Contract End Date:
12/31/2020
Current Contract Value:
$263,488
Expenditures:
$263,488

* Expenditures data includes accruals and are based on data through 31-Mar-2025.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
MarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarkerMarker
50 km
50 mi
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Sandra Fife Bonneville Power Administration Yes COR safife@bpa.gov (503) 230-3678
Arleen Henry Nez Perce Tribe Yes Administrative Contact arleenh@nezperce.org (208) 621-3833
David Johnson Nez Perce Tribe No Supervisor davej@nezperce.org (208) 621-3736
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Travis Kessler Bonneville Power Administration Yes Env. Compliance Lead tdkessler@bpa.gov (503) 230-5468
Joseph Oatman Nez Perce Tribe Yes Contract Manager joeo@nezperce.org (208) 843-7320x3730
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Jack Yearout Nez Perce Tribe Yes Contract Manager jacky@nezperce.org (208) 621-4638


Viewing 10 of 10 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A199473185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.$9790.35%04/01/202012/31/2020
B199474165Produce Environmental Compliance DocumentationProduce Environmental Compliance DocumentationWork under this contract involves only monitoring of Nez Perce treaty fisheries; such fisheries are guided by ESA Biological Assessments and Tribal Resource Management Plans. The harvest monitoring activities do not involve the direct sampling of live fish. The harvest monitoring work by nature will not induce direct or indirect mortalities to listed fish.$3,2441.16%01/01/202012/31/2020
C199475119Manage and Administer ProjectsProject Management & Planning plus Budgetary ProcessesPrepare Draft Scope of Work and Budget for FY20, submit financial reports and proper invoices.$13,3884.79%01/01/202012/31/2020
D199476156Develop RM&E Methods and DesignsDevelop annual harvest monitoring methodologyThis Work Element addresses the need to assure a well-designed sampling effort to obtain reliable harvest data that are essential for stock assessment and adult fish harvest and hatchery management activities. Achieve objective of implementing statistical survey methods to estimate harvest in specific tributaries and to assist in evaluating impacts of planned fisheries on populations/stocks being harvested in treaty fisheries. Harvest monitoring of tribal fisheries relies upon run-size and run-size estimates for those salmon and steelhead stocks/populations produced in BPA-funded hatcheries that support fisheries. Pre-season and early in-season run-size estimates provided by the Technical Advisory Committee under the US v Oregon process, including co-manager stock forecasts and discussions at subbasin scale, are integrated into implementation of the harvest monitoring methodologies.$25,4179.09%01/01/202012/31/2020
E199477157Collect/Generate/Validate Field and Lab DataImplement harvest monitoring methodology and disseminate harvest monitoring results (Creel Survey)On the ground harvest monitoring using the Creel Survey protocol will be implemented by developing a training program based on literature review, current sampling plan, and past monitoring experience. Monitoring will focus on specific Nez Perce Tribe Snake River Basin tributary fisheries for spring/summer Chinook salmon (aggregate Clearwater River) and steelhead/fall Chinook (aggregate Clearwater/North Fork Clearwater). Data is entered and stored in two places depending upon the fishery: (1) standard Excel spreadsheet and (2) a harvest database being developed and maintained at CRITFC; harvest summary reports will be supplied to cooperators on a regular basis.$70,91125.36%01/01/202012/31/2020
F199478157Collect/Generate/Validate Field and Lab DataImplement Harvest Monitoring Methodology and Disseminate Harvest Monitoring results (In-season)On the ground harvest monitoring using the In-season Interview Survey protocol will be implemented by employing a training program based on literature review, current sampling plan, and past monitoring experience. Areas/species monitored will include Clearwater Spring Chinook and South Fork Salmon River spring/summer Chinook (other Salmon Subbasin tributaries if possible). Data will be entered and stored in two places depending upon fishery: (1) standard Excel spreadsheet and (2) a harvest database being developed and maintained at CRITFC; harvest summary reports will be supplied to cooperators on a regular basis.$99,76735.68%01/01/202012/31/2020
G199479157Collect/Generate/Validate Field and Lab DataImplement Harvest Monitoring Methodology and Disseminate Harvest Monitoring Results (Post-season)Harvest monitoring using the Post-season Interview protocol will be implemented by employing a training program based on literature review, current sampling plan, and past monitoring experience. Areas/species monitored will include Snake River Basin Steelhead, Chinook salmon (spring, summer and fall-runs), and Coho salmon, to the extent practicable and available (primarily harvest of fish produced by BPA funded hatcheries, but it is expected that estimates will also be completed for other areas/species). Data will be entered and stored in two places depending upon fishery: (1) standard Excel spreadsheet and (2) a harvest database being developed and maintained at CRITFC; harvest summary reports will be supplied to cooperators on a regular basis. In future, the objective of the project is to transition to the use of a harvest database to complete this work element.$33,55412.00%01/01/202012/31/2020
H199480157Collect/Generate/Validate Field and Lab DataImplement Harvest Monitoring methodology and Disseminate Harvest Monitoring Results (Gill net)On the ground harvest monitoring using Gill Net In-season Survey protocol will be implemented by employing a training program based on literature review, current sampling plan, and past monitoring experience. Areas/species monitored will include Snake River Basin spring/summer Chinook, Snake River fall chinook and steelhead in the mainstem Snake and Clearwater rivers, and Zone 6 spring management period (primarily Ceremonial and Subsistence permit fishing). Data will be entered and stored in two places: (1) standard Excel spreadsheet and (2) a harvest database being developed and maintained at CRITFC; harvest summary reports will be supplied to cooperators on a regular basis. In future, the objective of the project is to transition to the use of a harvest database to complete this work element. For now, the estimates generated by the harvest database will be verified using the standard Excel harvest estimators (to ensure estimates are correct).$20,5807.36%01/01/202012/31/2020
I199481202Produce BiOp RPA ReportBiOp RPA Report for CY 2016Projects that have claimed that they support one or more RM&E RPAs (i.e., RPAs 50-73) under the FCRPS BiOp are required to report their results. To facilitate the summary of these results across the entire Columbia River Basin, and to provide more clarity as to the format required under the BiOp, these reports are required to be completed online. If desired, the required information can be prepared in MS Word, and pasted into cbfish.org. For more guidance see https://www.cbfish.org/Content/tutorials/Reporting_Guidance_BiOp_2013.pdf.$8,3883.00%01/01/202012/31/2020
J199482132Produce Progress (Annual) ReportSubmit Progress Report for the period (DEC 2017 - Nov 2018)The progress report summarizes the project goal, objectives, completed and uncompleted deliverables, problems encountered, lessons learned, and long-term planning. Examples of long-term planning include future improvements, new directions, or any ramping up or ramping down of contract components or of the project as a whole. Non-technical Progress Reports must conform to BPA guidelines. See the "Non-technical Progress Report" link at: http://www.cbfish.org/Help.mvc/GuidanceDocuments. RM&E Technical Progress reports must conform to BPA guidelines. See the "RME Technical Reporting" link at: http://www.cbfish.org/Help.mvc/GuidanceDocuments.$3,3881.21%01/01/202011/30/2020
      
$279,616
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance Documentation B: 165. Produce Environmental Compliance Documentation 12/31/2020 12/31/2020
Project Management, Planning and Budgetary Processes C: 119. Project Management & Planning plus Budgetary Processes 12/31/2020 12/31/2020
Develop Harvest Monitoring Methodology D: 156. Develop annual harvest monitoring methodology 12/31/2020 12/31/2020
Implement Harvest Monitoring Methodology and Produce accessible, error-checked datasets E: 157. Implement harvest monitoring methodology and disseminate harvest monitoring results (Creel Survey) 12/31/2020 12/31/2020
Implement Harvest Monitoring Methodology and Produce accessible, error-checked datasets F: 157. Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring results (In-season) 12/31/2020 12/31/2020
Implement Harvest Monitoring Methodology and Produce accessible, error-checked datasets G: 157. Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring Results (Post-season) 12/31/2020 12/31/2020
Implement Harvest Monitoring Methodology and Produce accessible, error-checked datasets H: 157. Implement Harvest Monitoring methodology and Disseminate Harvest Monitoring Results (Gill net) 12/31/2020 12/31/2020
Submit BiOp RPA Report in Taurus I: 202. BiOp RPA Report for CY 2016 12/31/2020 12/31/2020
Completed Annual Report J: 132. Submit Progress Report for the period (DEC 2017 - Nov 2018) 11/30/2020 12/31/2020

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 Produce Environmental Compliance Documentation
C 119 Project Management & Planning plus Budgetary Processes
D 156 Develop annual harvest monitoring methodology 11/07/2019
E 157 Implement harvest monitoring methodology and disseminate harvest monitoring results (Creel Survey) 11/07/2019
F 157 Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring results (In-season) 11/07/2019
G 157 Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring Results (Post-season) 11/07/2019
H 157 Implement Harvest Monitoring methodology and Disseminate Harvest Monitoring Results (Gill net) 11/07/2019
I 202 BiOp RPA Report for CY 2016